TIME AND WORK Continued.....
Today we
will look at some hard type of problems in time and work.
EG 1— If 12 men can complete a piece of work in 4
days, while 15 women can complete the same work in 4 days. 6 men start working
on the job and after working for 2 days, all of them stopped working. How many
women should be put on the job to complete the remaining work, if it is to be
completed in 3 days??
SOLUTION
Given,
12 men è4 days to
complete whole work
15 women è4 days to complete whole work
To
complete work,
6 men worked è 2days and left
?? women required è 3 days to complete REMAINING work
Now,
12 men è4 days
15 women è4 days
Therefore,
1man è 12*4 = 48m
1woman è 15*4 = 60w
So,
48m = 60w
i.e 4m = 5w --(i)
NOTE :-- We need to understand that how much work was
completed and how is remaining.
So,
6 men
completed SOME work in 2 days
We will find out this SOME WORK first.
6 men è 2 days
i.e 6*2 = 12m work
was completed (out of 48m work).
Therefore,
48m – 12m
= 36m work is REMAINING (out of 48m work).
Now,
4m =
5w ---from (i)
i.e 36m = 45w
So we can also say 45w work is remaining out of 60w work.
We need,
?? women è 3 days to
complete 45w work
i.e ?? women =
45 / 3
= 15 days
EG 2 - P, Q and R begin to finish a work
together. P is twice as efficient as Q and R is 2/3rd as efficient as Q. P
leaves after 2 days while Q leaves after 4 days. How many days will R further
take to finish off the work, if Q alone can finish the work in 16 days??
SHORTCUT
Given,
P =
2Q (P is twice as efficient as Q)
R = 2/3 * Q (R
is two-third as efficient as Q)
Q è 16 days to
complete work alone
P leaves after 2 days and
Q leaves after 4 days.
Now,
P = 2Q therefore P takes ½
time compared to Q
R = 2/3 *Q therefore R takes 3/2
time compared to Q
[TIME is inversely proportional to EFFICIENCY]
Also,
Q è 16 days alone ---(Given)
Therefore,
P è 16 * ½ è 8 days alone and
R è 16 * 3/2 è 24 days alone
Now just think don’t write anything,
P è 8 days to completes whole i.e 100% work
P è 2 days to completes
25% work
Similarly,
Q è 16 days to completes
whole i.e 100% work
Q è 4 days to completes
25% work
Therefore total work completed by P and Q is, 25% + 25% = 50%
SO, 50% more is REMAINING.
Which R has to complete.
R è 24 days to completes whole i.e 100% work
R è 12 days to completes
REMAINING 50% work
[12 days are 50% of 24 days.]
Out of 12 days R has worked for 4 days with P and Q.
Hence,
12
-4 = 8 days
No comments:
Post a Comment